Question: 2. Given the following project's activities table, complete the following: Sketch the network diagram Draw the network diagram with activity boxes Determine early start and

2. Given the following project's activities table, complete the following:
Sketch the network diagram
Draw the network diagram with activity boxes
Determine early start and finish times (forward pass)
Determine late start and finish times (backward pass)
Calculate the float
Find the critical path(s) of the project
Draw the bar chart for the project
Determine the late start calendar dates for all activities with float
If the project begins on October 1, 2022, what date will it end if no work is done on weekends or holidays? (Holidays include Nov. 11, 24, 25)
3. Create a bar chart
ActivityABCDEFGHIJKLMNPActivityDescriptionExcavateLaythefoundationPutuptheroughwallPutuptheroofInstalltheexteriorplumbingInstalltheinteriorplumbingPutuptheexteriorsidingDotheexteriorpaintingDotheelectricalworkPutupthewallboardInstalltheflooringDotheinteriorpaintingInstalltheexteriorfixturesInstalltheinteriorfixturesCloseOutImmediatePredecessorsABCCEDE,GCF,IJJHK,LM,NEstimatedDuration2410645797452627 ActivityABCDEFGHIJKLMNPActivityDescriptionExcavateLaythefoundationPutuptheroughwallPutuptheroofInstalltheexteriorplumbingInstalltheinteriorplumbingPutuptheexteriorsidingDotheexteriorpaintingDotheelectricalworkPutupthewallboardInstalltheflooringDotheinteriorpaintingInstalltheexteriorfixturesInstalltheinteriorfixturesCloseOutImmediatePredecessorsABCCEDE,GCF,IJJHK,LM,NEstimatedDuration2410645797452627