Question: 2 Identify the critical path (15 Points) Task ID Duration Predecessor 100 3 None 200 5 100 300 1 200 400 4 100 500 3

2 Identify the critical path (15 Points) Task ID

2 Identify the critical path (15 Points) Task ID Duration Predecessor 100 3 None 200 5 100 300 1 200 400 4 100 500 3 100,400 600 3 300 700 2 500,600 800 4 500 700 O 100-200-500-700-800 O 100-200-300-600-700-800 O 100-400-500700-800 fting 100-300-500-700-800