Question: 2 . If the work time in one day is 5 0 0 minutes for a machine, and this machine could be run for 4

2. If the work time in one day is 500 minutes for a machine, and this machine could be run for 400 minutes due to setup, maintenance and downtimes, the planned production amount during this 400 minute operation time is 300 parts but only 250 parts could be produced, and the rate of parts with acceptable quality is 99%, what is the OEE for this machine?