Question: 2. On average, a project management office (PMO) completes 300 projects per year. The average number of projects on the department's plate is 588 projects.
2. On average, a project management office (PMO) completes 300 projects per year. The average number of projects "on the department's plate" is 588 projects. The PMO head claims that average time to complete a project is less than six months. Do you agree with his claim or not? Why or why not? (4 points) Hint: Do not forget to convert the units in dimension of the parameters, if needed toward making the right conclusion