Question: 2 points QUESTION 12 The relationship between the natural variation in the production system and the products design specifications can be quantified using: Six Sigma

2 points

QUESTION 12

  1. The relationship between the natural variation in the production system and the products design specifications can be quantified using:

    Six Sigma

    Control charts

    A process capability index

    Fishbone diagrams

3 points

QUESTION 13

  1. To avoid shortsighted decision making, Balanced Scorecard measures performance in these areas: financial, customer, internal business process, and organizational learning & growth.

    True

    False

2 points

QUESTION 14

  1. When selecting appropriate control charts to use for variable data, you should consider what your sample size is and whether your data are normally distributed.

    True

    False

2 points

QUESTION 15

  1. Key aspects of the theory of constraints include identifying the bottlenecks in the process and balancing the work flows in the system.

    True

    False

2 points

QUESTION 16

  1. Business Process Design (also known as reengineering) usually involves reorganization of activities to be more process-centered.

    True

    False

2 points

QUESTION 17

  1. Six Sigma (DMAIC) is best applied when:

    There is too much variation in the process.

    There is too much waste in the process.

    The process is brand new.

    The process is fundamentally flawed.

3 points

QUESTION 18

  1. If a process is performing at the 6 sigma level, this means no more than 3.4 defects per million opportunities to fail taking into account up to 1.5 standard deviations of process drift.

    True

    False

2 points

QUESTION 19

  1. If Cp is less than 1, then process variability is greater than the customer's tolerance specs (can't satisfy customer); if Cp is greater than 1, you might be able to satisfy the customer.

    True

    False

2 points

QUESTION 20

  1. Takt time is calculated as

    Demand volume divided by customer required volume

    Customer required volume divided by available work time

    Available work time divided by customer required volume

    Available work time divided by demand volume

3 points

QUESTION 21

  1. A Gantt chart is a diagram that clarifies the interdependency of activities (which tasks must be completed before other tasks may begin) and shows where the critical path lies.

    True

    False

2 points

QUESTION 22

  1. ISO 14000 is an international standard to help organizations improve their quality performance.

    True

    False

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!