Question: 2 points The table below shows the tasks required to assemble a widget in your factory. Currently you have six employees each assigned to one

2 points
The table below shows the tasks required to assemble a widget in your factory. Currently you have six employees each assigned to one task.
\table[[Task 1,Task 2,Task 3,Task 4,Task 5,Task 6],[24 Minutes,13 Minutes,26 Minutes,21 Minutes,19 Minutes,27 Minutes]]
What is the capacity utilization for Task 2?(Express percentage as .9999 not 99.99%)
 2 points The table below shows the tasks required to assemble

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer