Question: ( 2 points ) Use the project plan and the calendar to answer the question - If the duration for the Complete Business Case is

(2 points) Use the project plan and the calendar to answer the question - If the duration for the "Complete Business Case" is four days, what should be the start and end dates?
September 2020
\table[[,Sun,Mon,Tue,Wed,Thu,Fri,Sat],[,,,1,2,3,4,5],[,6,7,8,9,10,11,12],[,13,14,15,16,17,18,19],[,20,21,22,23,24,25,26],[,27,28,29,30,,,],[,,,,,,,]]
\table[[,Task Name,Duration,Start Date,Finish Date,Predecessors],[1.,Create Project Charter,3 days,91?2020,93?2020,],[2.,Design Project Management Plan,5 days,94?2020,911?2020,1],[3.,Generate Feasibility Study,7 days,914?2020,922?2020,2],[4.,Complete Business Case,4 days,5-2,4,3],[5.,Planning Complete,0 days,N/A,NA,1,2,3,4
 (2 points) Use the project plan and the calendar to answer

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!