Question: 2. Prepare a network diagram for this project. The standard working week is 40 hours working Monday through Friday, 8 hours each day. Tasks with
2. Prepare a network diagram for this project. The standard working week is 40 hours working Monday through Friday, 8 hours each day. Tasks with duration not dependent on resources assigned are listed as calendar day duration. An example is awaiting arrival of a part in shipment from a supplier


Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
