Question: 2 . Product Y is made from one component P , three components Q , and two components R . P is made from two
Product Y is made from one component P three components Q and two components R P is made from two part S Q is made from S and R is made from two part S and three part T Other data inclues:
Part Lead Time Lot size Onhand Scheduled Receipts Safety stock
Y lotforlot none
P none none
Q none
R none none
S week
T none
a Complete the MRP explosion for product Y Identify any problems and discuss possible solutions.
b The supplier for part S informs you that the sheduled reeipt for that par will be week lae. What problems does it cause and what possible alternatives are open to you?