Question: 2. Project Scheduling PERT/CPM A project manager, dealing with a project with uncertain activity times, identified the following activity information for this project. a) Draw
2. Project Scheduling PERT/CPM A project manager, dealing with a project with uncertain activity times, identified the following activity information for this project.

a) Draw the project network.
b) Prepare the activity schedule?
c) What are the critical activities, what is the expected project completion time, and the variance on critical path?
\begin{tabular}{|c|c|c|c|c|} \hline Activity & ImmediatePredecessor & Optimistictime(Weeks) & Mostprobabletime(Weeks) & Pessimistictime(Weeks) \\ \hline A & - & 1.5 & 2.0 & 2.5 \\ \hline B & A & 2.0 & 2.5 & 6.0 \\ \hline C & - & 1.0 & 2.0 & 3.0 \\ \hline D & C & 1.5 & 2.0 & 2.5 \\ \hline E & B,D & 0.5 & 1.0 & 1.5 \\ \hline F & E & 1.0 & 2.0 & 3.0 \\ \hline G & B,D & 3.0 & 3.5 & 7.0 \\ \hline H & G & 3.0 & 4.0 & 5.0 \\ \hline I & F,H & 1.5 & 2.0 & 2.5 \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts