Question: 2 pts D Question 47 A factory making integrated circuits starts 500 of the wafers used in the circuits each day. This start rate has

2 pts D Question 47 A factory making integrated
2 pts D Question 47 A factory making integrated circuits starts 500 of the wafers used in the circuits each day. This start rate has been steady for many months. Management has tracked the work-in-process in the factory and found it to average 1,000 wafers. What is the flow time for a wafer passing through the factory? O 0.5 O2 0 1 O 5 can't decide