Question: 2 Question 2a, 2b, and 2c Use the information you have calculated to answer 2d and 2e. 4 points Question 2d The critical path is

2 Question 2a, 2b, and 2c Use the information you
2 Question 2a, 2b, and 2c Use the information you
2 Question 2a, 2b, and 2c Use the information you have calculated to answer 2d and 2e. 4 points Question 2d The critical path is "O 1-2-3-5-7 O 1-2-3-5-6-7 O 1-2-4-6-7 O 1-2-3-6-7 O 1-2-3-4-6-7 eBook References Question 2e The project duration is days. 2. Given the following information for a project: Immediate Predecessor(s) Time (in days) 4 4 3 Activity 1-2 2-3 2-4 3-4 3.5 3-6 4-6 5-6 5-7 6-7 4 S 5 2 4 3 4 1-2 1-2 2-3 2-3 2-3 2-4, 3-4 3-5 3-5 3-6, 4-6,5-6