Question: 2) Select the statement that best describes how a technical team member participates in Earned Value Management (EVM) analysis: [Recognize typical Program Management Office Integrated

2) Select the statement that best describes how a technical team member participates in Earned Value Management (EVM) analysis: [Recognize typical Program Management Office Integrated Product Team member roles in EVM analysis.] O Interpreting the technical performance measures (TPMs) and correlating them to cost and schedule variances O Determining if sufficient funds are available in each fiscal year O Approving over target baselines (OTBs) O Approving the contractor's Earned Value Management System (EVMS)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts