Question: 2. (SHOW YOUR COMPLETE WORK) A project network is shown below, with three different time estimates (Optimistic Time-Most Likely Time-Pessimistic Time (in days)) for each

2. (SHOW YOUR COMPLETE WORK) A project network is2. (SHOW YOUR COMPLETE WORK) A project network is

2. (SHOW YOUR COMPLETE WORK) A project network is shown below, with three different time estimates (Optimistic Time-Most Likely Time-Pessimistic Time (in days)) for each activity in the network. Use the PERT analysis results in (c) and (e) above to answer questions (f), (g), (h), and (i) below: f. What is the probability that the project can be completed within 34 days of its start? [4 points] g. What is the probability that the project can be completed within 25.5 days of its start? [5 points] h. Determine the project deadline that gives this project a 66% chance of on-time completion. [5 points] i. Determine the project deadline that gives this project an 11% chance of on-time completion. [6 points]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!