Question: 2) The roll-up schedule below outlines a maintenance project. After 6 weeks on the project, the actual costs to date is $43,560.00. Based on a

2) The roll-up schedule below outlines a
2) The roll-up schedule below outlines a
2) The roll-up schedule below outlines a
2) The roll-up schedule below outlines a
2) The roll-up schedule below outlines a
2) The roll-up schedule below outlines a maintenance project. After 6 weeks on the project, the actual costs to date is $43,560.00. Based on a review of the project, activities A, B, and C are 100% complete. Additionally, activities D and E are 75% complete, and activity F is 25% complete. No other activities or work have started. Complete the four multiple-choice questions for a project status report. Duration Bed Activity (Weeks) Cost 1 $2,500 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 B 2 B $6,700 $7,000 7 D -3 D E 2 E F 5 F G 2 $15,600 $11,000 525.000 525,000 $12,000 $10.500 $5,300 G 4 H 1 2 1 J 6 1 1 $2,500 What is the budget cost of work and the earned value of the project? Select one: BCWS = $ 39,500.00 BCWP = EV = $ 42500.00 O b. BCWS = $ 40,800.00 BCWP = EV = $ 42400.00 O c. BCWS = $ 40,800.00 BCWP = EV = $ 45400.00 O d. BCWS = $ 40,500.00 BCWP = EV = $42400.00 Oe. BCWS = $ 41,800.00 BCWP = EV = $ 42000.00 Calculate the schedule variance and percent schedule variance. Select one: O a. SV = $2,200 % SV = 5.65 % O b. SV = $2,200 % SV = 5.39 % O c. SV = $2,000 % SV = 5.35 % O d. SV = $2,154 % SV = 5.39% O e. SV = $1,950 % SV = 5.30 % Calculate the cost variance and percent cost variance. Select one: O a. CV= + $ 1,160 % CV = + 2.74% O b. CV = - $ 1,160 % CV = + 2.85% O c. CV=- $ 1,160 % CV = -2.74% O d. CV=- $ 1,160 % CV = -2.85% O e. CV = - $ 1,190 % CV = -2.74% Calculate the percent complete and planned percent complete? Select one: O a. PC = 34.44 % PPC = 33.14 % O b. PC = 32.54 % PPC = 33.14 % O c. PC = 33.14 % PPC = 34.44 % O d. PC = 33.44 % PPC = 34.14% O e. PC = 34.44 % PPC = 35.15 %

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!