Question: 2. The table below shows the different job orders accepted from different clients by MetFab Shop with the processing time and due dates that are
2. The table below shows the different job orders accepted from different clients by MetFab Shop with the processing time and due dates that are required per job. ( C2 )
| Jobs | Processing Time ( Days) | Due Dates ( Days) |
| A | 8 | 15 |
| B | 12 | 28 |
| C | 15 | 30 |
| D | 10 | 38 |
| E | 9 | 22 |
Being new in the MetFab, you want to identify what is the best sequence to use that will meet the deadline or if not possible, the least delays that you can suffer.
Interpret the data from the table above and compare which among the FCFS, SPT and EDD rules will be better in terms of average flowtime, average tardiness and average no of jobs in work center. ( C4 ) (15 pts : 5pts - Recommendation and its justification, 3 pts for the comparison matrix , 12 pts computation ( 4pts each )