Question: 2 - ( worth 2 0 points ) The Good - to - Go Suitcase Company makes three kinds of suitcases: ( 1 ) Standard,
worth points The GoodtoGo Suitcase Company makes three kinds of suitcases:
Standard, Deluxe, and Luxury styles. Each suitcase goes through four production
stages: cutting and coloring, assembly, finishing, and quality and packaging.
The total number of hours available in each of these departments is and
respectively. Each Standard suitcase requires hours of cutting and coloring, hours of
assembly, hour of finishing, and hours of quality and packaging. The corresponding
numbers for each Deluxe suitcase are hour, hours, hours, and hours,
respectively. Likewise, the corresponding numbers for each Luxury suitcase are hour,
hours, hours, and hours, respectively.
The sales revenue for each type of suitcase is as follows: Standard $ Deluxe $
and Luxury $ The material coits are Standard $ Deluxe $ and Luxury $
The hourly cost of labor for each department is cutting and coloring $ assembly $
finishing $ and quality and packaging $
The Excel layout and LP Sensitivity Report of GoodtoGo's problem are shown in
Screenshots A and B respectively. Each of the following questions is independent
of the others.
a What is the optimal production plan? Which of the resources are binding?
b Suppose GoodtoGo is considering including a polishing process, the cost of which
would be added directly to the price. Each Standard suitcase would require minutes
of time in this treatment, each Deluxe suitcase would need minutes, and each Luxury
suitcase would need minutes. Would the current production plan change as a result
of this additional process if hours of polishing time were available? the polishing
hourly cost is $ Explain your answer. tip: this is a new constraint that you should add
to the original problem
c Now consider the addition of a waterproofing process where each Standard suitcase
would use hour of time in the process, each Deluxe suitcase would need hours,
and each Luxury suitcase would require hours. the waterproofing hourly cost is $
Would this change the production plan if hours were available? Why or why not?
tip: this is a new constraint that you should add to the original problem
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock