Question: 2 . Your project involves developing a software application with 2 0 0 features. The project is budgeted at $ 1 , 0 0 0

2.Your project involves developing a software application with 200 features. The project is budgeted at $1,000,000 and is scheduled to be completed in 16 weeks. After 8 weeks, you have completed 80 features and have spent $450,000. Determine the value for each of the terms below:
a. Budget at Completion (BAC)
b. Planned Value (PV)
c. Earned Value (EV)
d. Actual Cost (AC)
e. Cost Variance (CV)
f. Schedule Variance (SV)
g. Cost Performance Index (CPI)
h. Schedule Performance Index (SPI)