Question: #20) - Based on the below information, prepare the Fixed Overhead Budget Variance and the Fixed Overhead Volume Variance: Total Budget Fixed OH for month
| #20) - Based on the below information, prepare the Fixed Overhead Budget Variance and the Fixed Overhead Volume Variance: | ||||||||
| Total Budget Fixed OH for month | $ 39,000 | Budget | ||||||
| Total budgeted labor hrs | ||||||||
| for the month (600 units @ 6.5 hrs/unit) | 3,900 | hrs | ||||||
| Predetermined FOH rate (POHR) | $ 10.00 | per DL hr | ||||||
| Actual FOH for month | $ 40,000 | Actual | ||||||
| Actual production for month | 600 | Units | ||||||
| Standard DL Hrs Allowed for | ||||||||
| actual production for month | ||||||||
| (600 units @ 7hrs/unit) | 4,200 | hrs | ||||||
| Applied FOH | ||||||||
| (3,900 DL hrs x $10 DL hr) | $ 42,000 | Applied | ||||||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock