Question: 20 min left QUESTION 9 late finish (LF-EF) Float can be calculated by either Subtracting the activity's early start from its late start (LS-ES) and/or
20 min left

QUESTION 9 late finish (LF-EF) Float can be calculated by either Subtracting the activity's early start from its late start (LS-ES) and/or Subtracting the activity's early finish from its True O False QUESTION 10 Which of the following are a level of estimation? O A. Ballpark O B. Order of Magnitude O C. Detailed O D. All of the above QUESTION 11 In order to implement a project, the WBS must be converted into an operating timetable otherwise known as a O A. Network Diagram O B. Critical Path O C. Project Schedule O D. Microsoft Project Save A