Question: (20 points) Consider this given project, please conduct the following analysis Indes Tasks Immediate Duration Predecessors (in week) Market Research 8 B Cost Analysis 4

(20 points) Consider this given project, please conduct the following analysis Indes Tasks Immediate Duration Predecessors (in week) Market Research 8 B Cost Analysis 4 Product Design A, B 12 D Development Analysis 10 E Developing Product Model D 8 F Filing Contracts E 12 G Product Testing E 10 H Pricing E 8 1 Sales/Marketing Planning GH 6 J Sales Force Training F.1 a. (5 points) Draw the network representation b. (5 points) Identify the critical path and the minimum project duration C. (10 points) Calculate the earliest and latest starting finishing time of each activity