Question: 20. Your current project is an $400,000 software development effort, with one team of programmers that will work for three months, at a total of

20. Your current project is an $400,000 software
20. Your current project is an $400,000 software development effort, with one team of programmers that will work for three months, at a total of 2,000 hours. According to the project schedule, your team should be done with 35% of the work. You find that the project is currently 45% complete. You've spent 70% of the budget so far. calculate the BAC, PV, EV, SV, CV, SPI,CPI and the status of the project? (show all the steps required to solve it) (8 Points) Enter your