Question: 2.1 What is the projects critical path and what is its length? 2.2 What is the normal cost of the project? 2.3 Crash the project

2.1 What is the projects critical path and what is its length?

2.2 What is the normal cost of the project?

2.3 Crash the project (shorten the project duration) by 3 days. List the activities for the first, second, and third crashes and the total crash (additional) cost.

2.1 What is the projects critical path and what

Cost Information Normal Duration Total Cost (in Activity (day) $US) A 4 $ 1,000 B 6 $ 1,800 4 2,500 Duratio n (day) 3 3 3 Crash Cost per Day? = 1000/1 $ Crashed Total Cost (in No. of Days Available $US) for Crashing? 2000 =4-3 3000 4000 determine the rest 6500 yourself 4500 7000 3000 D E F G 9 8 5 A A A A $ $ $ 2,700 2,400 3,500 2,400 6 6 3 1 1 B (6) E (8) A (4) D (9) F(5) G (2) C (4)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!