Question: 21. You have just started a project. The project team member reported that 20 percent of the project is done in 2 months by 10
21. You have just started a project. The project team member reported that 20 percent of the project is done in 2 months by 10 persons. If you want to complete project in 4 monthis how many persons, you should add to team? ( 4 Points) a. 20 b. 15 c. 10 d. 7 e. 5
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock