Question: 22. Sam, the warehouse manager with authority to commission projects, decided to upgrade the company's logistical software based on a business analyst's recommendation. Sam hired
22. Sam, the warehouse manager with authority to commission projects, decided to upgrade the company's logistical software based on a business analyst's recommendation. Sam hired William as the project manager and asked him to develop the project charter. After the project charter has been approved by Sam, William completed the Identify Stakeholders process. Before project planning begins, what should William do? Question 9Answer a. Hold a project kick-off meeting b. Inform the key stakeholders of the approved project charter c. Perform the Plan Stakeholder Engagement process d. Conduct stakeholder analysis