Question: 2-(25) consider the following table(information) Find activity time for each activity (te) Find the variance of each activity Find the critical path Find the probability
2-(25) consider the following table(information)
Find activity time for each activity (te)
Find the variance of each activity
Find the critical path
Find the probability of completing the project in 21 periods.
Solution:
| Act. ID | Description | Predecessor | Optm. (a) | Most Likely (m) | Pess. (b) | Act time te | Variance [(b-a)/6]2 | Critical |
| 1 | Design Package | None | 1 | 2 | 3 |
|
|
|
| 2 | Design Product | 1 | 2 | 3 | 4 |
|
|
|
| 3 | Build Package | 1 | 3 | 4 | 5 |
|
|
|
| 4 | Secure Patent | 2 | 4 | 5 | 6 |
|
|
|
| 5 | Build Product | 2 | 5 | 6 | 7 |
|
|
|
| 6 | Paint | 3,4,5 | 6 | 7 | 8 |
|
|
|
| 7 | Test Market | 6 | 2 | 2 | 2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock