Question: 23. A schedule update is: (2 Points) a. A schedule with resources and budget b. A schedule that reflects new design modifications c. A revised
23. A schedule update is: (2 Points) a. A schedule with resources and budget b. A schedule that reflects new design modifications c. A revised schedule reflecting project information at a given data date regarding completed activities, in-progress activities, and changes in future work