Question: 23. Consider a project to develop a software application. The project starts with A1: Requirement Analysis, which takes 3 days. A2: Design follows Requirement
23. Consider a project to develop a software application. The project starts with A1: Requirement Analysis, which takes 3 days. A2: Design follows Requirement Analysis and takes 10 days. Two modules need to be developed after the Design activity: A3: Module-1 Development takes 15 days. A4: Module-2 Development takes 20 days. A5: Documentation runs after the Design activity and takes 5 days. A6: Integration starts after both the Module Development activities A3, A4, and takes 10 days. A7: Document Update (5 days) and A8: Deployment (6 days) start after the integration activity. Clearly, Document Update is further dependent on the completion of Documentation. A9: User Training starts after the Document Update activity and takes 7 days. A10: Closing starts when Deployment and User Training are complete and takes 1 day. a. Create an activity network for the project. b. Develop a dependency matrix for the project. c. What are the earliest start time, earliest complete time, latest start time, lates complete time, and slack time for each activity?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts