Question: 23. The PM has all the subject matter expert input for the task durations, for the tasks on the critical path, the PM received the

23. The PM has all the subject matter expert

23. The PM has all the subject matter expert input for the task durations, for the tasks on the critical path, the PM received the following input. what is the expected completion time of the project? Task Min A 2 B 4 5 D 3 E 4 Likely Max 4 9 5 10 9 15 4 7 8 13