Question: 23 When are project managers assigned to a project? After the Project Charter has been approved During the Concept phase As soon as possible and

23 When are project managers assigned to a project? After the Project Charter has been approved During the Concept phase As soon as possible and before the Planning phase begins Before the Project Charter is developed