Question: 23-3 PLEASE ANSWER EACH REQUIREMENT Data Table Standard Cost Information Quantity Cost 0.15 per part 8.00 per hour 9.00 per hour Direct Materials 2 parts
23-3 PLEASE ANSWER EACH REQUIREMENT




Data Table Standard Cost Information Quantity Cost 0.15 per part 8.00 per hour 9.00 per hour Direct Materials 2 parts 0.02 hours .02 hours Direct Labor Variable Manufacturing Overhead0.02 hours Fied Manufacturing Overhead Fixed Manufacturing Overhead ($29,100 for static budget volume of 97,000 units and 1,940 hours, or $15 per hour) Actual Cost Information Direct Materials Direct Labor Variable Manufacturing Overhead (210,000 parts 0.20 per part) 42,000 (1,640 hours@ 8.10 per hour) 13,284 8,000 L Fixed Manufacturing Overhead Fixed Manufacturing Overhead 28,000 . Print Done