Question: 2.4. The table below represents project information pertaining to the ABC Project. Use the information in the table below to draw the Gannt chart for
2.4. The table below represents project information pertaining to the ABC Project. Use the information in the table below to draw the Gannt chart for the ABC Project. (10 marks) 9 10 Task Mode Task Name 4ABC Project Task A Task B Task C Task D Milestone Task E Taks F Task G Milestone Duration 31 days 9 days 4 days 5 days 3 days 0 days 4 days 3 days 7 days 0 days Finish Predecessors Wed 2/14/24 Fri 1/12/24 Start Tue 1/2/24 Tue 1/2/24 Tue 1/9/24 Fri 1/12/24 Mon 1/15/24 2,3 Fri 1/19/24 Mon 1/22/24 Wed 1/24/24 4 Thu 1/25/24 Thu 1/25/24 5 Thu 1/25/24 Wed 1/31/24 Tue 1/30/24 5 7 Fri 2/2/24 Tue 2/13/24 8 Mon 2/5/24 Wed 2/14/24 Wed 2/14/24 9