Question: 24. The WBS is a. a chart showing the flow of work from the start to the end of the project. b. a chart showing

 24. The WBS is a. a chart showing the flow of

24. The WBS is a. a chart showing the flow of work from the start to the end of the project. b. a chart showing the hierarchical listing of all the tasks and sub-tasks to be performed c. a narrative (text) description of all the tasks and sub-tasks to be performed. d. a chart showing the timeline of activities for the life of the project. e. a and d, only