Question: 26. Mark is trying to determine the probability that a particular path of activities can be completed in a 22 day time period. Path A-C-E
26. Mark is trying to determine the probability that a particular path of activities can be completed in a 22 day time period. Path A-C-E has an expected path duration of 24 days. Activity A has a variance of 3.55, C has a variance of 1.76 and E has a variance of 3.34. What is Marks answer in percentage?