Question: 26 Risk avoidance can be done by all that which of the following actions? Select one O a extending the schedule O b. reducing project

26 26 Risk avoidance can be done by all that which
Risk avoidance can be done by all that which of the following actions? Select one O a extending the schedule O b. reducing project scope O c. creating contingency funds O d. clarifying requirements o e, all of these are risk avoidance actions