Question: 26. Suppose that the critical path through a project network is: A-C-E. Using the probabilistic three-time-estimate method for activity times (assuming the Beta probability distribution),

26. Suppose that the critical path through a

26. Suppose that the critical path through a project network is: A-C-E. Using the probabilistic three-time-estimate method for activity times (assuming the Beta probability distribution), the following results were calculated: Activity Mean time in weeks | Variance in (mean duration times 20 4 42 16 38 16 C E Then the probability of completing the entire project in less than 91 weeks is A. 0.0668 B. 0.1587 C. 0.4013 D. 0.8413

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!