Question: 27. A Project Manager learns that it took three days to level and prepare a one-acre site for the foundations of a building and therefore
27. A Project Manager learns that it took three days to level and prepare a one-acre site for the foundations of a building and therefore estimates it would take six days to prepare the two-acre site she is working on currently. The estimation technique used here is known as: Parametric estimating Analogous estimating Bottom-up estimating Conservative estimating Top-down estimating