Question: ??????? 29. CAPM and Hurdle Rates. A project under consideration has an internal rate of return of ( 14 % ) and a beta of
??????? 29. CAPM and Hurdle Rates. A project under consideration has an internal rate of return of \( 14 \% \) and a beta of .6. The risk-free rate is \( 4 \% \), and the expected rate of return on the market 2 answers