Question: 2A) Draw & fill out a network diagram using the below information. Unless otherwise noted, assume relationships are finish-start with O lag/lead. Make sure you

2A) Draw & fill out a network diagram using the

2A) Draw & fill out a network diagram using the below information. Unless otherwise noted, assume relationships are finish-start with O lag/lead. Make sure you identify all dependencies, ES/EF/LS/LF/Dur/SL for each activity Activity Predecessor Activities A B C D E F G H A fs+4, B SS+2 B, C D ff+4 E ESS+1 F, G H SS+4,1 Duration (weeks) 4 5 2 4 3 4 6 10 4 4 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!