Question: 2.Tebogo Projects secured a 5 year maintenance contract with the government. The contract is worth R10 MILLION spread equally over the duration. An annual 10%
2.Tebogo Projects secured a 5 year maintenance contract with the government. The contract is worth R10 MILLION spread equally over the duration. An annual 10% inflation is allowed on the project. Calculate the total project cost after 5 years. [10]