Question: [ 3 0 points ] An app design project consists of following activities. Times are given in weeks. table [ [ Activity , Description,
points An app design project consists of following activities. Times are given in weeks.
tableActivityDescription,tableImmediatePredecessortableOptimisticTimetableMost LikelyTimetablePessimisticTimeAProb. Def.,BSys Analysis,ACDesign IOBDDesign DBBEDevelop Input,CFDevelop Output,CGDevelop DBDHTest System,E F GIImplement,H
a Calculate the expected activity duration variance for each activity, ES EF LS and LF times and the slack for each activity. Show the values in a table activity schedule What is the critical path for the project? Show all work to earn credit.
b Using MS Project or any other software create a Gantt chart for the project based on LS and LF times.
c What is the probability of completing the project in weeks? Show all work.
d Which activities would you focus on in order to get the project back on schedule? Why? Explain in sentences.
e Assume that "Systems Analysis" B actually finished at weeks, "Design IOC actually finished at weeks, and "Design Database" G actually finished at weeks. Note that this is not the duration of activity Recalculate the expected project completion time. Show all work.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock