Question: 3 0 . You are in the process of developing the project charter for an energy project. Which of the following is NOT a typical

30. You are in the process of developing the project charter for an energy project. Which of
the following is NOT a typical element found in the project charter?
A. Acceptance criteria
B. Project approval requirements
C. Project exit criteria
D. Measurable project objectives and related success criteria
31. The project kick-off meeting is usually associated with the end of planning and start of
executing. As the project manager, you will use the kick-off meeting for all of the following
outcomes EXCEPT:
A. To communicate the objectives of the project.
B. To gain the commitment of the team for the project.
C. To explain the roles and responsibilities of each stakeholder.
D. To formally authorize the existence of the project
32. Which of the following best describes the proper role of the project manager as related
to changes? :
A. Make changes as and when it occurs.
B. Estimate the impact of the change on the project objectives.
C. Prevent unnecessary changes.
D. Notify senior management about changes
33. The project charter has been developed, and the project has been formally authorized.
A full-time project manager is appointed for the project. There is clarity about the business
needs, high-level project description, and product requirements that the project is to
address. A summary budget has also been approved. Given this information, what activity
should the project manager perform NEXT from the available options?
A. Perform the work defined in the project management plan to achieve the p roject`s
objectives.
B. Define, prepare and coordinate all subsidiary plans and integrate them into a
comprehensive project management plan
C. Monitor and report the progress to meet the performance objectives defined in the
project management plan.
D. Define scope and get the project scope statement so that you can understand how much
effort is needed for the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!