Question: 3 - 1 0 . A 2 0 , 0 0 0 - square - foot warehouse was just constructed for $ 8 0 0

3-10. A 20,000-square-foot warehouse was just constructed for $800,000. If the cost-capacity factor is 0.83, what is the estimated cost to construct a 30,000-square-foot warehouse? (3.4.1)
 3-10. A 20,000-square-foot warehouse was just constructed for $800,000. If the