Question: 3 1 2 points When a project team elects to purchase insurance, or adopts a fixed price contract with a vendor, or hires an expert,
points
When a project team elects to purchase insurance, or adopts a fixed price contract with a vendor, or hires an expert, it is demonstrating which of the following risk response strateg,
Avoid a threat
Assume a threat
Mitigate a threat
Transfer a threat