Question: 3 . 1 5 A machine shop has four machines of five different types and operates 4 0 hours per week. Part - mix ratios,

3.15
A machine shop has four machines of five different types and operates 40 hours per week. Part-mix ratios, batch quantities, part routings, machines, servers, and production times are given in the table below for the five part styles produced in the shop. Operation sequence for each part style is in the order of station number. Part styles are identified by letter and stations are identified by number. Determine (a) which station is the bottleneck, (b) total production rate of all five parts, (c) production rates of each of the five part styles, (d) utilization of each server at each station, and (e) average utilization of the machine shop.
\table[[Part style (j),A,B,C,D,E
 3.15 A machine shop has four machines of five different types

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!