Question: 3 . 1 8 ( A ) A batch of parts is routed through six machines in a batch production plant. Batch size is 1

3.18(A) A batch of parts is routed through six machines in a batch production plant. Batch size is 100. At each machine, the parts are processed sequentially. Setup times and cycle times are given in the table below. Average nonoperation time per machine is 12hr.
Determine the (a) manufacturing lead time and (b) hourly production rate for operation 3.
\table[[Machine,1,2,3,4,5,6],[Setup time (hr),4.5,2.0,5.0,3.0,2.5,4.0],[Cycle time (min),5.0,3.5,6.2,1.9,4.1,2.5]]