Question: 3 1 . Arranging the schedule where tasks that are normally done in sequence are done in parallel is a schedule compression technique called _

31. Arranging the schedule where tasks that are normally done in sequence are done in parallel is a schedule compression technique called ____
a. Crashing
b. Floating
c. Fast Tracking
d. Leveling