Question: 3 1 For the jobs listed below, which processing sequence would result using Johnson's rule? table [ [ Processing time ( hrs ) ]

31
For the jobs listed below, which processing sequence would result using Johnson's rule?
\table[[Processing time (hrs)],[Job,Center :,Center 2],[a,6,11],[b,12,8],[c,5,9],[d,10,7]]
Multiple Choice
c-a-d-b
b-d-a-c
a-b-c-d
d-c-b-a
c-a-b-d