Question: 3. (10 points) Examine the following dependency matrix: Project Activity time Predecessors A B C E F G (Days) Successor A 2 B 4
3. (10 points) Examine the following dependency matrix: Project Activity time Predecessors A B C E F G (Days) Successor A 2 B 4 X C X 2 X E 1 X F X X G X (a) What is the project completion time? Your Answer (b) What is the critical path? Your Answer (c) What are the slack times for activity C and F? Your Answer