Question: 3. (1.7 pts. total) For the network shown in the figure below: B D F Finish 2 5 6 A Start 1 C E
3. (1.7 pts. total) For the network shown in the figure below: B D F Finish 2 5 6 A Start 1 C E 3 3 a) Calculate the Early and Late Start and Finish times of each of the activity. (1.2 pts.) b) Calculate and note the slack for each activity on the diagram. (0.3 pts.) c) What is the critical path of this project? (0.1 pts.) How long will the project take (project completion time)? (0.1 pts.)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
